Steelwork ’21-’22

Q

Steelwork ’21-’22

30 Mar 2022

Steelwork, winter 2021/2022

October 16, 2021 is the time to bring the QUADRA to the SRF shipyard in Harlingen. Time to do all the steelwork on the hull. Unfortunately, the parts for the new superstructures and the extension of the stern have not yet been delivered. But luckily there is still plenty of other work to do first, such as removing the old superstructures, moving the tanks, placing the bulkheads and building the engine room. After this work is finished, a temporary floor is laid and it suddenly becomes visible how much space there is in the QUADRA.

 

A closer inspection of the deck reveals it to be somewhat thin and dented and very difficult to get even. A minor setback, but replacing the deck completely would also save a lot of other work, such as blasting the inside, so that choice was made quickly. And so all that remains is a large bathtub. But not for long. Piece by piece the new deck frames are placed and then the deck.
It is now January and the new steelwork parts have finally been delivered and the always hard-working steel worker Arjoderik can easily continue welding the parts together.

And then comes the most exciting part at the end of January: the extension of the stern. The new stern is assembled and ready to be weld to the ship. But then it turns out it doesn’t fit. After a lot of measuring, puzzling, consulting the drawings and consultation with the design office, it turns out that there is a mistake in the drawing. A small mistake with big consequences. Again measuring, puzzling and doing. Thanks to the craftsmanship of Arjoderik and André and many hours of extra work later due to all the adjustments, the QUADRA has a beautiful new extended stern.
Then it goes fast. One superstructure after another is placed, just like the cockpit. It is becoming more and more visible what the QUADRA will look like. But here too the consequences of the mistake in the drawing are noticeable and the necessary adjustments have to be made.
Before the doghouse is placed, the engine, generators and other large parts are first placed in the engine room.
After all the major steelwork is done, it’s time for the details and making the ship wind and watertight. Plus for a few coats of paint, so that the new steelwork is immediately well preserved.
After more than five months of hard work, the QUADRA leaves the shipyard on March 27, 2022 and her beautiful new lines are finally visible in full length for the first time.
Construction nearing completion

Construction nearing completion

The construction of the Quadra is nearing completion! The carpenter is finished and will only come once more for the final finishing touches. The lighting — both inside and out — is working, water flows from the taps, the ventilation system provides fresh air, and the...

A new look

A new look

From approximately mid-May to mid-July, Quadra's hull was renovated at Multiship. First, it was filled and sanded. Multiple times and multiple layers were applied until the hull was smooth and the transition to the new keel was smoothed. Then she was painted and...

Keel and masts

Keel and masts

Masts Below you can see the making of the masts and gaffs of the Quadra summarized in a few images. Unfortunately, it is difficult to visualize the amount of work: from drawing the designs, making the mast fitings and gaff fittings, cutting all the parts, delivering...

Interior carpentry

Interior carpentry

After the framework for the walls had been placed and the ship had been insulated in May 2024, carpenter Douwe started on the interior of the ship in June 2024. First, all the walls were placed, so that the layout was already clearly visible. Then the door frames and...

Work first half of 2024

Work first half of 2024

After the transfer of our charter ship Avatar to the new owners at the beginning of November 2023, we first took a well-deserved break. From January 2024, we continued the conversion of the Quadra full-time and have done a lot in the past six months. Partly thanks to...

Steelwork 2023

Steelwork 2023

On January 6, 2023, the Quadra was again towed to SRF shipyard for a new series of work. This time the rudder, propeller shaft, propeller, bow thruster tube, box coolers for the engine and generators, exhausts and other openings/valves in the underwater hull were...

Our partners

Our partners

The construction of the Quadra would not be possible without good partners. We would like to introduce the companies we work with below: Olivier van Meer DesignQuadra: 3D-scan & drawings The OVM office has been involved in the construction, conversion and refit of...

The construction has started – Our plans

The construction has started – Our plans

After almost a year, the Quadra was towed to the shipyard again last week. This time not for a paint job, but for the real thing: the construction of the sailing yacht is about to begin! In the past week all old superstructures have been removed from the deck, so that...